Floor repair is a complex and responsible stage in home or apartment renovation. The importance of a properly installed floor is hard to overestimate. Even the most expensive and exclusive wall finishes will not look as impressive if the floor has old, worn-out covering.

Modern flooring markets offer consumers an exceptionally wide range of materials to solve almost any task. On store shelves you can find everything – from exclusive parquet boards to economy-class linoleum. With such abundance, homeowners doing DIY renovations or clients commissioning floor repairs must simply choose the right material for each room in the house or apartment.

For rooms with high moisture levels, ceramic tiles are ideal as flooring; for children’s rooms and bedrooms, carpet tiles are suitable; for living rooms and offices, laminate parquet is recommended. The choice of flooring should balance practicality, comfort, and the homeowner’s budget.

A Good Floor Is a Flat Floor

Before selecting and installing new flooring, old flooring must be removed, and this is the perfect opportunity to assess the condition of the subfloor – whether it is level and solid. If the base has slopes, unevenness, or mechanical damage (cracks, chips, etc.), this is the ideal moment to restore it to proper condition.

Most apartment floors are built on concrete slabs using self-leveling screed. The choice of dry construction mixes for floor leveling is now very broad – just pick the one you like best.

Floor leveling occurs in two stages. First, a rough leveling compound up to 50 mm thick is poured. After drying and curing, a finish leveling compound 5–30 mm thick is applied. Typically, screeds 5–8 cm thick fully dry and are ready for final flooring installation within 5–7 days. Crucially, leveling guides (‘masti’) must be installed before pouring to ensure the floor level is maintained during the pour.

Laminate Parquet Installation

This article focuses on floor repair using laminate parquet as an example. Below is a step-by-step guide to installing laminate flooring – one of the most popular types of flooring in recent years.

The advantages of laminate over other flooring types are obvious: it’s easy to clean, maintains a new appearance for years, and has the natural look and texture of real wood. The list could go on, but let’s move on to describing the floor repair process via laminate parquet installation.

First, a base layer made of foamed polyethylene or extruded polystyrene must be installed under laminate flooring. The base thickness should be 2–3 mm. This base layer is crucial as it acts as a shock-absorbing foundation for the entire floor structure, improving sound insulation and load distribution.

Second, a key rule for laminate installation must be remembered: the flooring must not touch the wall. A gap of at least 5 mm between the wall and the edge of the laminate is required. This accounts for thermal expansion of the material when indoor temperatures rise. If the floor is installed tightly against the wall, it may buckle or lift at joints during hot weather.

Step-by-Step Laminate Installation

  • Installation begins in the far-left corner of the room relative to the entrance door. Several laying patterns exist, but the most popular are those with symmetry in every second or third row.
  • Before starting, it’s advisable to purchase a special kit of ‘spacers’ to adjust the gap between laminate panels and walls. The most critical step is installing the first three panels: two in the first row and one in the second. These set the overall direction of the floor pattern.
  • Panels are inserted at a 45-degree angle and snapped into the locking mechanism. Any slight deviation in geometry will prevent the lock from closing, so precise cutting and measuring is essential.
  • Second and third rows are installed with joints offset by one-third. This means that in the second row, one-third of the first panel’s length is cut off, and in the third row, two-thirds. This pattern is both visually appealing and structurally strong, ensuring proper joint interlocking.
  • These first three rows are installed from left to right. Cut-off pieces should not be discarded, as they are clean thirds and can be used as finishing elements on the opposite side of the floor. Accuracy in measurement is critical, as previously noted.

Finally, here are several recommendations that will significantly simplify laminate installation. Cutting panels – which are dense and strong – is best done with an electric jigsaw using a blade with teeth pointing upward (backward). This ensures a clean edge and prevents chipping, unlike manual sawing.

It’s best to buy laminate for the entire area with a 5–7% buffer. We strongly advise against purchasing flooring in parts, as different production batches may result in color variation. Also, ensure that each 'tongue-and-groove' edge on the panels has been treated with a wax or paraffin compound – this enhances water resistance during floor cleaning. Discard any panels with damaged locking edges, as defects like these occasionally occur even in high-end laminate.