How to Make a Concrete Floor Screed
Level the floor and prepare the surface for the flooring – these are the main functions of a screed. It is a labor-intensive and expensive process. However, if you are confident in your abilities, you can do it yourself.
Let’s examine a typical screed example. First, a bit of theory. In rooms, several types of screeds are commonly used:
- cement-sand,
- concrete,
- anhydrite,
- epoxy,
- mosaic, and others.
Now, self-leveling floors – screeds based on leveling compounds – are also widely used. Screeds are also divided into rigid and floating types. The first type involves laying the screed directly on the slab, while the second involves placing the screed on a layer of waterproofing or thermal insulation.
Choose the type of insulation and determine its necessity based on living conditions. If the area under the floor is a basement, a thermal insulation layer may be helpful. If noisy neighbors live on the lower floor, a sound insulation layer can help reduce noise transmission.
Preparatory Work
Concrete screeding should be done in a dry, draft-free room with closed doors and windows. The ideal temperature for work ranges from 10 to 25 degrees Celsius.
Before pouring the screed, prepare the base. Clean the surface thoroughly: remove debris, dust, and loose concrete fragments. If there are cracks in the slab, seal them with a thick mortar. Apply a primer to the base surface.
To prevent walls from absorbing moisture, apply waterproofing: cover the walls along the room’s perimeter with a strip of roofing felt. The top edge of the strip should be about 15 cm above the planned screed level.
If an insulation layer is planned, apply it immediately after priming the floor.
Next, determine the so-called zero level. Use a construction level for this. Choose any convenient mark above the floor. Mark it on the wall (at two or three points), then transfer it to other walls using the level. Then connect the marks with a meter-long ruler.
Take measurements from the zero level to determine the maximum and minimum distances to the floor base. The arithmetic average of these two values will serve as the basis for adjusting the future screed thickness.
Starting the Process
Before pouring, install guide profile bars (masons' guides) on the floor. Use a special metal profile. Fix it level using thick mortar or screws. The distance between the bars should be calculated based on the length of the straightedge (a tool for leveling the mix). It should be 30–40 cm shorter than the straightedge.
The next step is preparing the mix. Use a powerful electric drill with a mixer attachment. Follow the instructions on the material packaging carefully. The final mix should be like thick dough. Note: use it within one to one and a half hours.
Then begin laying and leveling the mix. Pour the mix onto a floor area of about 1–1.5 square meters and level it manually with a trowel. Final leveling is done using a straightedge that glides between two guide bars.
What to Pay Attention To
Remember that after laying, you must remove excess air from the mix. You can use a needle roller or poke the mix with a metal rod.
It’s advisable to have a helper: one person prepares the mix, the other lays and levels it. All work should be completed within one day. After the screed is complete, dampen it once or twice during drying (roll over the surface with a damp roller) to prevent cracks.
Under ideal conditions, the mix drying process takes three to four weeks. Of course, few people wait a full month, so flooring installation usually begins about one week after the screed.